Acrow Bridge Enables Rapid Road Restoration After Flood

Acrow temporary bridges offer relief after flooding

Extensive rains resulted in destruction of structure following dam breach

Heavy rains and floodwater in May 2020 in Michigan, led to the collapse of the Edenville Dam. The Michigan Department of Transportation (MDOT) and local officials had to close nearly 30 roads and bridges, including two locations along the M-30 corridor. Entire communities were divided, forcing commuters and local residents to follow lengthy detours. 10,000 people were immediately displaced and one of the area’s main bridges, the M-30 causeway bridge spanning the Tobacco River, was completely destroyed.

Design and construction of a permanent replacement would take years. With no reasonable local detour route, MDOT decided on a long-term temporary structure to restore mobility as quickly as possible and mitigate extended economic damage. A pre-engineered modular steel 230 foot (70.1m) Acrow bridge was procured.

It is expected to be in service for up to 3 years, but designed to last a minimum of 15 years should long-term construction plans be suspended. This allows MDOT time to analyze the current and future transportation needs of the corridor. Acrow’s durable modular steel bridges offer ideal, immediate solutions for restoring damaged or destroyed infrastructure. In-stock components can be delivered quickly and easily, even over damaged roads.

Construction on the project began in December 2020; the bridge delivered to contractor, Anlaan Corporation, the following month. Despite adverse weather, the span was opened to traffic in March 2021, less than a year after the floods, rather than the standard three to five years design and approval process. When the permanent bridge is opened, the modular bridge will be disassembled and the components stored for reuse in planned and emergency projects across the state.