Back to Case Studies

Acrow Case Study

I-75 Florida Case Study

Temporary Multi-Span Continuous Panel Bridge

Saves Construction Time During I-75 Widening and Renovations

The 320 foot long Acrow 700XS 3-span bridge being used on Interstate 75 over Bruce B. Downs Boulevard was purchased by the Florida DOT. It provides for north bound traffic on I-75 allowing for the replacement of the existing bridge and improvements to the Bruce B. Downs Boulevard intersection.

The total project construction cost is $95.6 million and covers 11.4 miles. The Florida DOT is widening I-75 from four to six lanes from Fowler Avenue in Hillsborough County to State Road 56 in Pasco County. When finished there will be at least three through-lanes in each direction, with auxiliary lanes near interchanges to improve traffic flow entering and exiting the highway. Included in the project are three new bridges, including the replacement of the bridge over Bruce B. Downs Blvd as well as improvements to the intersections of I-75 at Fowler Avenue, Bruce B. Downs Blvd and the westbound Fowler Ave bridge over the Hillsborough River.

The bridging purchased by the Florida DOT is the first Acrow 700XS series bridge purchased and owned by the Florida DOT. The main reason for specifying a panel bridge was founded in the history of the Florida DOT’s utilization of state owned Acrow 300 Series bridging. The state purchased its 300 Series bridging in the 1980’s and 1990’s and has successfully utilized its inventory for planned detours and emergency response, which includes 3,400 feet of the I-10 bridge over Pensacola Bay after Hurricane Ivan in 2004. The Florida DOT currently maintains an inventory of close to 8,000 feet of Acrow 300 series bridge that is regularly used throughout the state. All of the inventory of 300 series bridge has a roadway width of 24 feet and is only designed and rated for an HS-20 live load and bridge spans no longer than 60 feet.

The recently purchased 700XS bridging is significant in that it indicates the state’s desire to continue utilizing truss panel bridging for detours on roadways, including highways. Truss panel bridging has the versatility to meet today’s heavy loads and guard rail requirements, provide longer spans, and offer a choice of widths to accommodate varying levels of daily traffic volume.

Once the designs were finalized, contract documents were published and the project was advertised for bidding. The state awarded the $95.6 million project to Prince Contracting with Corporate offices located in Tampa, Florida. The Florida DOT, purchased the Acrow bridge which was installed in January 2012.

You also might be interested in

See All